More
    HomeTopicsEnergyȘtefăniță Munteanu, Transelectrica: “The Suceava–Bălți power line will be ready within 24...

    Ștefăniță Munteanu, Transelectrica: “The Suceava–Bălți power line will be ready within 24 months”

    Published on

    The Suceava–Bălți power line is set to enter the construction phase, with completion expected within 24 months, while Transelectrica is advancing major transmission infrastructure projects under a ten-year investment plan exceeding 2 billion euros.

    “The greatest satisfaction when you take part in investments is seeing them put into practice,” Ștefăniță Munteanu, Chairman of Transelectrica’s Executive Board said during the Energy for Romania event, organised by Electrica.

    “We are about to start construction. We have all the necessary documents, including building permits. This line is being built, and it is happening. It will be ready within 24 months,” the Transelectrica executive stated.

    The project is part of the company’s broader transmission network development programme, which involves investments of more than 2 billion euros over the next ten years. Munteanu noted that the plan is regularly updated to reflect evolving infrastructure needs.

    He also pointed out that all of Transelectrica’s major transmission line projects have been awarded and are at various stages of implementation.

    “Some are already under construction, and we are closing the 400 kV transmission ring, including the Gădălin–Suceava section, for which we are awaiting the building permit,” he explained.

    In the Banat region, all project sections are currently under construction, while another major investment is the Alba Iulia substation. Describing it as a particularly challenging undertaking, Munteanu highlighted its complexity and digital infrastructure.

    “It is a difficult, complex project, a very complex one – a digital substation. It has a contractor, and work is underway,” he said.

    Munteanu also addressed the challenges faced by Romania’s electricity transmission system during a period of exceptional pressure, following the temporary withdrawal from operation of Cernavodă Nuclear Power Plant’s Units 1 and 2.

    He said that the simultaneous absence of the two units from the electricity system for three months had not been anticipated even in the most pessimistic scenarios, placing additional pressure on both the transmission and distribution networks.

    “We have come through a so-called emergency period, and Transelectrica has risen to the challenge. Even the darkest scenarios did not envisage Units 1 and 2 at Cernavodă being out of the system for three months. The entire pressure was transferred to the grid – both the transmission grid and the distribution grid,” Munteanu said.

    He stressed that the experience demonstrated the ability of transmission and distribution operators to manage significant fluctuations in system demand.

    “Transelectrica, my colleagues and everyone working in distribution know how to cope with pressure. Because we are talking about real pressure, driven by the need for electricity, not any other kind of pressure,” he concluded.

    Latest articles

    George Agafitei, PPC Romania: “We cannot move forward without investing in the grid”

    Romania needs to approach energy security from a regional perspective rather than focusing exclusively...

    Mihaela Suciu, DEER: “Romania’s economic growth depends entirely on grid development”

    Romania’s economic growth and reindustrialisation depend directly on the modernisation and expansion of electricity...

    Corina Popescu, Moldelectrica: “Moldova’s true energy independence will come when the Suceava–Bălți interconnection is completed”

    Completing the Suceava–Bălți power line will be a key step towards strengthening the Republic...

    IULIUS is preparing a new generation of projects, investing upwards of €1.3 billion in urban development and local communities

    IULIUS Company is consolidating its development strategy through a series of ambitious projects designed...

    More like this

    George Agafitei, PPC Romania: “We cannot move forward without investing in the grid”

    Romania needs to approach energy security from a regional perspective rather than focusing exclusively...

    Mihaela Suciu, DEER: “Romania’s economic growth depends entirely on grid development”

    Romania’s economic growth and reindustrialisation depend directly on the modernisation and expansion of electricity...

    Corina Popescu, Moldelectrica: “Moldova’s true energy independence will come when the Suceava–Bălți interconnection is completed”

    Completing the Suceava–Bălți power line will be a key step towards strengthening the Republic...