    Construction of the Iernut power plant blocked by GEO 114/2018, says Romgaz

    Published on

    The project of the gas plant that Romgaz is building in Iernut is blocked at the moment, due to the provisions of GEO 114/2018 regarding the increase of salaries in construction, said Adrian Volintiru, CEO of Romgaz, e-nergia.ro reads.

    According to Volintiru, Romgaz will have to pay additional costs to those who carry out the construction works, but neither these companies have an updated situation.

    In 2016, the national gas producer, Romgaz, signed a contract worth 268 million Euro, excluding VAT, with the companies Duro Felguera and Romelectro, for the development of a new power plant for the production of electricity within the Iernut power plant. The plant should have been used by the beginning of 2020, according to the initial plans.

    Latest articles

    Dentons advises Kommunalkredit on the 50.6 million euros refinancing of the 60 MW Ruginoasa wind farm

    Global law firm Dentons has advised Kommunalkredit Austria AG on the 50.6 million euros...

    Executive changes at Allianz-Țiriac: Aurel Badea to step down after 33 years

    Allianz-Țiriac has announced upcoming leadership transitions set for late 2026 to ensure long-term organization...

    OMV Petrom acquires a 20 MW battery energy storage system for the Ișalnița solar park

    OMV Petrom and the Romanian company Simtel Team have signed an engineering, procurement and construction (EPC) contract for a...

    The first edition of the BusinessPedia Connect debates is hosted by the NBR Palace on September 15: Who takes Romania forward?

    BusinessPedia brings two generations of entrepreneurs and leaders to the NBR for a debate...

    More like this

    Dentons advises Kommunalkredit on the 50.6 million euros refinancing of the 60 MW Ruginoasa wind farm

    Global law firm Dentons has advised Kommunalkredit Austria AG on the 50.6 million euros...

    Executive changes at Allianz-Țiriac: Aurel Badea to step down after 33 years

    Allianz-Țiriac has announced upcoming leadership transitions set for late 2026 to ensure long-term organization...

    OMV Petrom acquires a 20 MW battery energy storage system for the Ișalnița solar park

    OMV Petrom and the Romanian company Simtel Team have signed an engineering, procurement and construction (EPC) contract for a...