    Delgaz Grid completes 4.7 million euros modernisation of Vicov substation in Suceava County

    Published on

    Distribution operator Delgaz Grid has completed the modernisation of the Vicov 110/20 kV substation in Suceava County, following an investment of 25.48 million RON (approximately 4.7 million euros). Of the total amount, 2.2 million euros came from European funds, with the remainder financed from the company’s own resources.

    The modernised substation will improve electricity distribution services for consumers in the area by reducing the risk of power supply interruptions and enhancing the quality of electricity delivered. Approximately 18,000 customers will benefit from the investment in the localities of Vicovu de Sus, Vicovu de Jos, Rădăuți, Brodina, Putna, Straja, Gălănești, Voitinel, Bilca, Ulma, Izvoarele Sucevei, Moldova Sulița, Moldovița, Vatra Moldoviței, Frumosu and parts of Frătăuții Noi.

    The main works involved replacing high- and medium-voltage equipment and integrating the new equipment into the SCADA (Supervisory Control and Data Acquisition) system, which enables remote monitoring and control of installations.

    The 17-kilometre Vicov–Rădăuți 110 kV power line was also modernised, and new connections were established between the Vicov, Rădăuți and Egger substations to improve the security and reliability of electricity supply.

    At the same time, the upgraded substation provides safer and more stable conditions for feeding electricity into the grid from 20 renewable energy producers, including hydropower and photovoltaic installations. The investment also contributes to reducing the distribution network’s own technological consumption and improving the performance indicators of the electricity distribution service.

    The company is currently implementing 16 other projects supported by European funding, with a combined value of 530 million euros, including 375 million euros in European funds. The projects cover the installation of smart meters, the modernisation and construction of transformer substations, and the upgrading of electricity networks across all voltage levels.

    Latest articles

    Filip & Company assists Autonom on the acquisition of Business Lease Romania

    Filip & Company law firm has provided legal assistance to Autonom Services S.A. in...

    Foreign Investors Council (FIC): Romania needs fiscal stability and competitiveness to go hand in hand

    With the new Government taking office, the Foreign Investors Council (FIC) reiterates that fiscal...

    Monsson launches its first energy storage project in Sweden, with 30 MW of power and 60 MWh of storage capacity

    Monsson announces the launch of Eskilstuna Power Reserve, its first investment in a battery...

    Christian Tour launches new digital travel platform in Romania

    The management of Christian Tour announces that, on October 26, it launched Vacanza.ro, a...

    More like this

    Filip & Company assists Autonom on the acquisition of Business Lease Romania

    Filip & Company law firm has provided legal assistance to Autonom Services S.A. in...

    Foreign Investors Council (FIC): Romania needs fiscal stability and competitiveness to go hand in hand

    With the new Government taking office, the Foreign Investors Council (FIC) reiterates that fiscal...

    Monsson launches its first energy storage project in Sweden, with 30 MW of power and 60 MWh of storage capacity

    Monsson announces the launch of Eskilstuna Power Reserve, its first investment in a battery...